Infrastructure
Oxagon
أوكساچون
Partially openTabuk
Partly operating: NEOM says the Port of NEOM has operated since 2022; the port told WorldCargo News (18 Sep 2026) its Terminal 1 container facility is still expected to open this year, and construction of a 100 MW first phase of an AI data centre began in September 2026.
- Core development area
- 48 km²
- Current port capacity
- 250,000 TEU
- Port capacity target by 2030
- 1.5 million TEU
Target: 2030 — Port of NEOM capacity target of 1.5 million TEU by 2030 (not a completion date for the whole city)
Approximate location
Sources (13) · Last verified 13 Oct 2026
- NEOM
- NEOM
- Saudi Vision 2030 (SPA) · 16 Nov 2021
- WorldCargo News · 18 Sep 2026
- DatacenterDynamics (DCD) · 7 Sep 2026
- AGBI
- AGBI
- Argaam · 15 Apr 2026
- Semafor · 22 May 2026
- Semafor · 7 Jun 2026
- AGBI
- Wikipedia via Kiwix mirror
- Wikipedia