Energy

Sudair Solar PV plant

سدير للطاقة الشمسية
OperationalRiyadh

The full 1,500 MW plant reached commercial operation when its third phase was certified on 3 Jan 2024 (Argaam, 3 Jan 2024).

Installed capacity
~1,500 MW
Full commercial operation
January 2024
Homes it can power
185,000 homes

The centre of the plant's outline as mapped in OpenStreetMap

Sources (9) · Last verified 14 Oct 2026
  1. Public Investment Fund · 8 Apr 2021
  2. Public Investment Fund · 8 Apr 2021
  3. ACWA Power · 15 Aug 2021
  4. Argaam · 3 Jan 2024
  5. EnterpriseAM · 4 Jan 2024
  6. Arab News · 30 Oct 2023
  7. ACWA Power
  8. Wikipedia
  9. OpenStreetMap contributors (ODbL)

A 1,500 MW solar photovoltaic plant in Sudair Industrial City, developed under PIF's renewables programme by a consortium led by ACWA Power.

Shape on the map: The plant's outline as mapped in OpenStreetMap — way 1317477364 (© OpenStreetMap contributors, ODbL)

Open on the map