Trojena

تروجينا
DelayedTabuk

Delayed: completion was originally targeted for 2026 (PIF, Mar 2022) and no revised date has been published; the 2029 Asian Winter Games were officially postponed (OCA and Saudi Olympic & Paralympic Committee, 24 Jan 2026) and awarded to Almaty (OCA, 5 Feb 2026); NEOM terminated Webuild's dams-and-lake contract (effective 29 Mar 2026); Semafor (22 May 2026, citing unnamed sources) reported no new investment until after 2030.

Maximum elevation
2,600 m above sea level
Original completion target
2026
Dam and lake contract terminated
Effective 29 March 2026

Target: 2026 — ORIGINAL official completion target stated in March 2022; it has lapsed and no revised official date has been published

The centre of the main works site as mapped in OpenStreetMap (approximate)

Sources (17) · Last verified 14 Oct 2026
  1. NEOM
  2. NEOM
  3. Public Investment Fund (PIF) · 3 Mar 2022
  4. Olympic Council of Asia (OCA)
  5. The New Arab · 24 Jan 2026
  6. The Peninsula · 24 Jan 2026
  7. Olympic Council of Asia (OCA) · 5 Feb 2026
  8. Dezeen · 6 Feb 2026
  9. Webuild · 25 Mar 2026
  10. AGBI · 26 Mar 2026
  11. Semafor · 22 May 2026
  12. Semafor · 7 Jun 2026
  13. Argaam · 15 Apr 2026
  14. AGBI
  15. AGBI
  16. Wikipedia
  17. OpenStreetMap contributors (ODbL)

A mountain destination in NEOM at altitudes of up to 2,600 m, planned for year-round outdoor activities including outdoor skiing in winter.