The whole Kingdom
From NEOM in the north to Soudah in the south.
- Operational2
- Partially open11
- Under construction4
- Planned1
- Delayed4
- Scaled back1
Swipe upScroll down1 of 23 · Tourism
The Red Sea
Partially openTabuk
Shura, the destination's hub island
- 11 (as of 1 Oct 2026)Resorts open
- 28,000 km²Total area
- 2023First guests
11 resorts open as of 1 Oct 2026; eight more due across Red Sea Global’s destinations.
Oct 20262017 announced2026 announced target
Next: AMAALA2 of 23 · Tourism
AMAALA
Partially openTabuk
- 7 (as of 1 Oct 2026)Resorts open
- 4,200 km²Total area
- 2026First guests
Seven resorts open as of 1 Oct 2026; AMAALA received its first guests in 2026.
Oct 20262018 announced2026 announced target
Next: Sindalah3 of 23 · Tourism
Sindalah
DelayedTabuk
The island
- About 840,000 m²Island area
- 86Marina berths
- Early 2024Original public opening target
Not opened since its Oct 2024 launch; Red Sea Global will take it over to assess completion.
Oct 20262022 announced2024 announced target
Next: THE LINE4 of 23 · Urban development
- 170 kmOriginal design length (2022)
- 9 millionOriginal planned population (2022)
- Not necessary, per PIF governor (Apr 2026)Completion by 2030
- Works along the route
- First two building strips
Work reportedly halted until after 2030; PIF’s governor said a 2030 finish is not necessary.
Oct 20262021 announcedno official date
Next: Oxagon5 of 23 · Infrastructure
Oxagon
Partially openTabuk
Mapped works (core area 48 km²)
- 48 km²Core development area
- 250,000 TEUCurrent port capacity
- 1.5 million TEUPort capacity target by 2030
Port operating since 2022 (NEOM); first container terminal still expected in 2026.
Oct 20262021 announced2030 announced target
Next: NEOM Green Hydrogen Company (NGHC)6 of 23 · Energy
NEOM Green Hydrogen Company (NGHC)
DelayedTabuk
- 600 tonnes/dayPlanned hydrogen output
- Up to 1.2 million tonnes/yearPlanned green ammonia output
- About 4 GWRenewable power capacity
Built and commissioning; commercial operation targeted for 2027, after a 2026 goal.
Oct 20262020 announced2027 announced target
Next: Trojena7 of 23 · Tourism
Trojena
DelayedTabuk
Mapped works (part of the destination)
- 2,600 m above sea levelMaximum elevation
- 2026Original completion target
- Effective 29 March 2026Dam and lake contract terminated
Was due in 2026; no new date published, and the 2029 Asian Winter Games went to Almaty.
Oct 20262022 announced2026 announced target
Next: AlUla – Journey Through Time Masterplan8 of 23 · Culture
AlUla – Journey Through Time Masterplan
Partially openAl Madinah
- 20 kmMasterplan corridor
- 7 hotels, about 1,000 keysOperating hotels (June 2026)
- 320,000Visitors in 2025
June 2026: an RCU official said AlUla runs 7 hotels and some projects slowed.
Oct 20262021 announced2035 announced target
Next: Rua Al Madinah Project9 of 23 · Urban development
Rua Al Madinah Project
Under constructionAl Madinah
Project area (approximate)
- 1.35 million m²Project area
- 47,000+Planned hotel and residential units
- SAR 8bn ($2.1bn)Superblock 5 contract (Apr 2026)
April 2026: a SAR 8bn contract was awarded to build Superblock 5, with 10 branded hotels.
Oct 20262022 announcedno official date
Next: Soudah Peaks10 of 23 · Tourism
- 636.5 km²Project area
- 2,810Planned hotel rooms
- 2027Phase 1 target completion
Dec 2025: a SAR 1.3bn deal was signed to build the power network for all project phases.
Oct 20262021 announced2033 announced target
Next: Sudair Solar PV plant11 of 23 · Energy
Sudair Solar PV plant
OperationalRiyadh
Plant limits
- ~1,500 MWInstalled capacity
- January 2024Full commercial operation
- 185,000 homesHomes it can power
The full 1,500 MW plant has been in commercial operation since Jan 2024.
Next: Qiddiya City12 of 23 · Tourism
Qiddiya City
Partially openRiyadh
Six Flags and Aquarabia, the first parts open
- 31 Dec 2025Six Flags Qiddiya City public opening
- 23 Apr 2026Aquarabia water park opening
- 500,000Projected residents
Six Flags opened Dec 2025 and Aquarabia Apr 2026; other parts remain under construction.
Oct 20262017 announcedno official date
Next: Diriyah13 of 23 · Culture
Diriyah
Partially openRiyadh
At-Turaif and mapped works (part of 14 km²)
- 14 km²Development area (Diriyah 1 and 2 masterplans)
- 2010At-Turaif inscribed on UNESCO World Heritage List
- 50 million a year by 2030Targeted annual visits
At-Turaif, Bujairi Terrace and Zallal are open; other districts are under construction.
Oct 20262017 announced2030 announced target
Next: New Murabba14 of 23 · Urban development
New Murabba
DelayedRiyadh
Mapped works and the Mukaab plot (part of 14.1 km²)
- 14.1 km²Area
- 400 mMukaab dimensions (height, width, depth)
- 2040 (was 2030)Revised full-completion date
Full completion reportedly moved to 2040; reports of a Mukaab pause are unconfirmed.
Oct 20262023 announced2040 announced target
Next: King Abdullah Financial District15 of 23 · Urban development
King Abdullah Financial District
Partially openRiyadh
District limits
- More than 1.6 million m²Total land area
- More than 630Operating hotel rooms (Sep 2026)
- SAR 12 billionFinancing facility for further development (Jun 2026)
Operating, with 630+ hotel rooms in service as of Sep 2026; development continues.
Oct 20262007 announcedno official date
Next: King Salman Park16 of 23 · Environment
King Salman Park
Under constructionRiyadh
Park wall (approximate)
- More than 17 million m²Area
- 95%Share of phase 1 and 2 contracts awarded
Much of phase one’s infrastructure is complete and planting continues; not yet open.
Oct 20262019 announcedno official date
Next: Sports Boulevard17 of 23 · Sports
Sports Boulevard
Partially openRiyadh
- More than 135 kmPlanned length on completion
- 85 kmPathways and tracks completed (Aug 2026)
- Feb 2025First phase opened (five destinations)
- Sports Boulevard Bridge
- The Promenade: cycling paths
- Sands Sports Park: cycling routes
Phase one open since Feb 2025; 85 km of a planned 135+ km of paths are complete.
Oct 20262019 announcedno official date
Next: ROSHN (SEDRA)18 of 23 · Urban development
ROSHN (SEDRA)
Partially openRiyadh
- 30,000 homesHomes at SEDRA
- 20 million m²Masterplan area
- 8 phasesPhases
SEDRA phase-two homes are being handed over; masterplan work continues.
Oct 20262020 announcedno official date
Next: King Salman International Airport19 of 23 · Transport
King Salman International Airport
Under constructionRiyadh
The existing King Khalid airport, around which the new one is built
- about 57 km²Masterplan area
- up to 185 million passengers a yearTarget capacity by 2050
- 4,200 m (construction began Dec 2025)Third runway length
Third-runway works began Dec 2025; Terminal 6 enabling contract awarded Jul 2026.
Oct 20262022 announced2030 announced target
Next: Expo 2030 Riyadh20 of 23 · Culture
Expo 2030 Riyadh
Under constructionRiyadh
Construction site (approximate)
- 1 Oct 2030 – 31 Mar 2031Expo dates
- about 6 million m²Site area
- 42 million+ visitsExpected visits
Earthworks done and utilities under way; major construction targeted for end-2029.
Oct 20262023 announced2030 announced target
Next: Riyadh Metro21 of 23 · Transport
Riyadh Metro
OperationalRiyadh
- 176 km (6 lines)Network length
- 85 stationsStations
- 300 million+ (as of 13 Oct 2026)Passengers since launch
- 1Blue
- 2Red
- 3Orange
- 4Yellow
- 5Green
- 6Purple
- Red Line extension to DiriyahUnder way · 8.4 km
All six lines are in service; the Red Line is being extended to Diriyah.
Next: Green Riyadh Program22 of 23 · Environment
Green Riyadh Program
Partially openRiyadh
Riyadh: the programme covers the whole city
- 7.5 million+ trees by 2030Tree target
- 1.7 m² to 28 m² (target)Green space per person
- 4.5 million+ (as of 13 Oct 2026)Trees planted
Over 4.5 million trees planted; afforestation covers 235 km of roads and corridors.
Oct 20262019 announced2030 announced target
Next: Riyadh Art23 of 23 · Culture
Riyadh Art
Partially openRiyadh
Riyadh: the programme covers the whole city
- 1,000+ public art installationsPlanned installations
- 75 works (Apr 2026)Permanent works installed
- 115 worksFurther works planned
75 permanent artworks installed across the capital, with 115 more planned.
Oct 20262019 announcedno official date
Next: The end of the journeyThe end of the journey
23 projects, one map
- 23
- projects
- about 3,300 km
- the journey’s route
- 212
- sources
Where they stand as of 14 Oct 2026
- 2 Operational
- 11 Partially open
- 4 Under construction
- 1 Planned
- 4 Delayed
- 1 Scaled back
Out of 23 projects.